安裝前需要做的準(zhǔn)備:
Preparation before installation:
1.建筑物圍護(hù)結(jié)構(gòu)施工完成,所有障礙物和雜物已清理,地面雜物均已清理!
1. The construction of building enclosure is completed, all obstacles and sundries have been cleared, and all sundries on the ground have been cleared!
2.凈化系統(tǒng)風(fēng)管安裝時(shí),建筑物內(nèi)部安裝部件的地面均已做好,墻面混凝土找平完畢,保證室內(nèi)無塵土或有防塵措施的條件下進(jìn)行。
2. During the installation of the air duct of the purification system, the floor of the internal installation parts of the building has been completed, and the wall concrete has been leveled to ensure that there is no dust or dust-proof measures in the room.
3.安裝地點(diǎn)輔材齊全,并有施工技術(shù)員進(jìn)行質(zhì)量和技術(shù)的指導(dǎo)。
3. The auxiliary materials at the installation site are complete, and the construction technicians provide quality and technical guidance.
風(fēng)管安裝注意事項(xiàng):
Precautions for air duct installation:
1.風(fēng)管內(nèi)嚴(yán)禁其他管線穿越
1. No other pipelines are allowed to cross the air duct
2.安裝在易燃、易爆環(huán)境下的風(fēng)管應(yīng)有良好的接地,通過生活區(qū)或者生產(chǎn)區(qū)的風(fēng)管安裝一定要嚴(yán)密,并且不能設(shè)備風(fēng)管接口。
2. The air duct installed in the flammable and explosive environment shall be well grounded. The air duct passing through the living area or production area must be tightly installed, and the air duct interface shall not be equipped.
3.室外立式風(fēng)管的固定不得與避雷針或房屋避雷設(shè)施連接到一起。
3. The fixing of outdoor vertical air duct shall not be connected with lightning rod or house lightning protection facilities.
4.風(fēng)管安裝符合以下技術(shù)規(guī)定:
4. The installation of air duct shall comply with the following technical regulations:
①風(fēng)管與通風(fēng)設(shè)備,配件連接的配置,不得縮小其連接部位的連接管。
① The configuration of the connection between the air duct and the ventilation equipment and accessories shall not reduce the connection pipe of its connection part.
②吊架不能設(shè)置在風(fēng)口、風(fēng)閥、檢查門及自控機(jī)構(gòu)處,不得固定在法蘭上,避免風(fēng)管變形影響風(fēng)管的作用。
② The hanger shall not be set at the air outlet, air valve, inspection door and automatic control mechanism, and shall not be fixed on the flange to avoid the effect of air duct deformation on the air duct.
③吊架安裝符合相應(yīng)的安裝規(guī)定,懸吊的風(fēng)管與部件應(yīng)設(shè)防止擺動(dòng)的固定點(diǎn),如固定支架、支撐等,固定點(diǎn)的設(shè)置位置和數(shù)量應(yīng)根據(jù)系統(tǒng)情況而定。
③ The installation of hangers shall comply with the corresponding installation regulations. The suspended air ducts and components shall be provided with fixed points to prevent swing, such as fixed supports, supports, etc. The location and number of fixed points shall be determined according to the system conditions.
④法蘭墊料和厚度根據(jù)輸送空氣溫度的不同,選擇的材質(zhì)也不同。
④ The flange gasket and thickness are different according to the temperature of the conveying air.
⑤風(fēng)管及部件穿墻、屋面時(shí),應(yīng)設(shè)置防雨罩,穿出屋面的風(fēng)管超過1.5m時(shí)應(yīng)拉索,拉索應(yīng)鍍鋅或用鋼絲繩,拉索禁止固定在風(fēng)管法蘭上,嚴(yán)禁拉在避雷針或避雷網(wǎng)上。
⑤ When the air duct and its components pass through the wall and roof, a rain cover shall be provided. When the air duct passing through the roof exceeds 1.5m, a stay cable shall be provided. The stay cable shall be galvanized or steel wire rope. It is prohibited to fix the stay cable on the air duct flange, and it is prohibited to pull it on the lightning rod or lightning protection network.
⑥柔性短管的安裝應(yīng)松緊適度,不得扭曲,可伸縮性的金屬或非金屬軟風(fēng)管的長度不宜超過2m,并不得有死彎及塌凹。
⑥ The flexible short pipe shall be installed with appropriate tightness and shall not be twisted. The length of flexible metal or non-metallic flexible air duct shall not exceed 2m, and there shall be no dead bend or concavity.
⑦保溫風(fēng)管的支、吊架宜設(shè)在保溫層的外部,并不得破壞保溫層。
⑦ The supports and hangers of thermal insulation air ducts should be set outside the thermal insulation layer and should not damage the thermal insulation layer.